Public Information

The Chestnut Run Energy project team thanks community members who participated in two Public Information Meetings held in December 2025. These meetings were conducted as planned and provided an opportunity to share information about the proposed project, its development status and timeline, and its potential economic value to the community. Attendees also had the opportunity to ask questions, provide comments, and discuss project planning and community benefits.

Both meetings were held in the elementary school cafeteria at Carrollton Exempted Village Schools.

Ohio Power Siting Board Applications

Chestnut Run Energy has submitted two applications for Certificate of Environmental Compatibility and Public Need to the Ohio Power Siting Board (Case No. 25-1065-EL-BGN for the generation facility and Case No. 25-1066-EL-BTX for the generation-tie line). If you would like to receive a hard or electronic copy of either application, please contact us using the phone number or the form via the “Contact Us” tab at the top of this page. Hard copies will be provided at cost.

Public Information Meetings #1 and #2 – Proposed Major Utility Facility

The first Public Information Meeting focused on notifying the public and soliciting input on the scope of the Chestnut Run Energy project. The discussion included details about the project and its associated generation tie line into the regional electric system.

Date Held: December 3, 2025
Time: 6 to 8 p.m.

The second Public Information Meeting presented the project in a manner consistent with the information included in the project application. This meeting also provided updates on the project’s status with the Ohio Power Siting Board (OPSB) and other regulatory authorities and included responses to questions raised during the first meeting as well as new inquiries.

Date Held: December 16, 2025
Time: 6 to 8 p.m.

We appreciate the time and input shared by all who attended these meetings. Please check back to this site for information about future public meetings and project updates.

Facility Application Meetings #1 and #2

The Ohio Power Siting Board (OPSB) conducted a local hearing for the Facility (Case No. 25-1065-EL-BGN) as part of the project’s application process. The local hearing was held at the Carrollton Elementary School cafeteria for the generation facility, and members of the public were encouraged to speak.

Date Held: May 21, 2026
Time: 6 p.m.

In addition, the OPSB conducted an adjudicatory hearing for the facility, whereby the project and subject-matter experts provided testimony on the project. The meeting was held at the office of the Public Utilities Commission of Ohio in Columbus.

Date Held: June 3, 2026
Time: 10 a.m.

Generation-Tie Application Meetings #1 and #2

The Ohio Power Siting Board (OPSB) conducted a local hearing for the generation-tie application (Case No. 25-1066-EL-BTX) as part of the project’s application process. The local hearing was held at the Carrollton Elementary School cafeteria for the generation facility and members of the public were encouraged to speak.

Date Held: June 18, 2026
Time: 6 p.m.

The OPSB held an adjudicatory hearing for the generation-tie, whereby the project and subject-matter experts provided testimony on the project. The meeting was held at the office of the Public Utilities Commission of Ohio in Columbus.

Date Held: July 7, 2026
Time: 10 a.m.

SITING WAIVERS

Requested Waivers: Chestnut Run has requested and received a waiver of the timing requirements in O.A.C. 4906-4-03(B)(1).

Contact Us

Comments or questions? We want to hear from you! Contact Us or call us at +1 (330) 238-3900.

*This content was updated on 11/12/25. Please check back regularly as we will provide additional updates when more information becomes available.

If you have specific questions for the Ohio Power Siting Board, you can contact the board directly.

Contact Ohio Power Siting Board

180 E Broad Street, Columbus OH 43215
Phone: (800) 686-7826
Email: contactOPSB@puco.ohio.gov
Website: https://opsb.ohio.gov/home/

  •      = Chestnut Run Energy Property (240 Acres)
  •      = Chestnut Run Energy Facility (30 Acres)
  •      = Generation Tie Line (2.2 miles, 9 properties crossed)
  •      = Switchyard (6 Acres)
  •      = Sensitive Receptors
  •      = Existing Gas Pipeline
  •      = Existing 345kV Lines
  •      = 2-Mile Radius
  •      = Township Border